Day 33 - More rafters fitted

A lot of wood work done today, though it's not as obvious a leap as we've seen in the past few days ! Rafters have been fitted now right along the South side, and a start has been made to joining up the new extension roof with the existing house. There's also been a bit of work involved in matching up the lengths of the rafters with the existing house roof-line, so they match.
The base foundation has also been poured for the heating oil tank. Not sure what happens with the bunding on this, though I suspect that tank is double skinned. Will need to find out a bit more there I think.