Thursday 21 October 2010

Day 124 - Flooring starts in front vestibule

Work continued with the oak flooring and associated doors & skirting today. The dining room is all but finished now, and work has now extended into the front vestibule. Still waiting on the 2 outstanding windows for the front vestibule, but we're expecting to see them early next week. That will allow the insulation to be completed there & the larch cladding to be done.
The painter was also here again & continued with the softwood staining & varnishing. Really looking good, and he's managed to get a good match to the oak flooring. The colour has warmed the rooms up a bit too.
Doug was here for a while, which was great as we got a chance to go through the build status & schedule what's coming up. We also made some decisions on the tiles required for the front entrance outside & the new rear door. Will get them ordered up tomorrow.

0 comments: