Although visually things don't look much different from yesterday, there's quite a lot happened ! The boards have been fixed along the South facing roof, ready for the membrane cover to go on, and there's been further work at the East side, with that area nearing completion. At the new rear doorway, the rafters have been installed (following re-shaping of the entrance, which had to be heightened).
Some more plywood facings were also installed, however I've a concern that a couple of these are visibly warped - may be due to the wet weather we've been having so may dry out ok, but to be checked further all the same.