Monday 10 May 2010

Day 9 - Further Brick Work

Despite some snow (!) the South & East foundation walls are now complete, and work has begun on the brick work within the extension boundary. Still to build at the front of the extension, but the aim is to have this all complete for Thursday to allow drains pipework to go in & the hardcore to backfill. After this the floor will be poured.
There's a bit more of a height difference between the garage & the existing house (500mm), necessitating 3 steps going into the link hall between the house & the garage/rear workshop. Should be ok.
Bit of debate ongoing regarding the set-up of the main bathroom. The room dimensions aren't as big as we first thought (always the way I guess once you start filling it with gear). We'll need to make our minds up soon though, before the drains are set !

0 comments:

Post a Comment