Wednesday 11 August 2010

Day 66 - Further boarding on 1st floor

Busy upstairs today and about 75% of the 1st floor has now been fitted with plaster board - though 3 sections of wall have had to be left for now as there will be radiators spotted there (plumber coming tomorrow to fit the pipes etc).
The sparkies finished today (for now) and have left all the tie in cables in the existing attic, including the telephone line. The joiners have pulled the relevant cables through the new plaster board upstairs.
Down stairs the final 2 windows were fitted to the work room at the front of the house, so that's looking a bit better. Just the external workshop/garage areas plus the main doors to go in now.
The weather today has been dreadful & it's rained pretty much all day. Not only has this delayed the painting (the painter went away in the morning), but it's also a real hassle as the slaters haven't completed the roof, and we're suffering from a couple of water leaks. This means we can't insulate & board those areas, which is a pain.

0 comments:

Post a Comment