Wednesday 7 July 2010

Day 49 - Garage roof almost complete

More work on the roof tiles today. The garage roof is now mostly done, with only some of the apex to complete & lower areas of the South side where it meets the workshop roof. Must say that the angled joins at the pyramid & the vee to the workshop look pretty rough. I'm sure this will be neatened up over the next few days (but will be checking !).
Some further joinery done at the new back door to the extension. Roof there now boarded, though there are a few more planks to go in. Some more facings to complete, but can't see it all being done by COP tomorrow, before the joiners head off on holiday. We'll see though.