Monday 26 July 2010

Day 53 - Work restarts after holidays !

Seems like ages since I've posted any progress updates (guess it has been ages really !!).
The lads came back from their holidays today, with a whole squad on site all day - great to be getting back into things. Joinery work progressed in the main, and now the soffits & facings have been completed along the South side & around the pyramid roof. Just some tidying up to complete around the garage roof, and the rear workshop.
Framework installation also commenced on the East walls in preparation for the larch cladding (which is still a wee bit off !). Good to see that starting though.
On the roof, finally the membrane has ben layed on the south side, which has been letting water in for ever - hopefully get the slaters back soon to complete the tiling job.