The plumber was back today & has installed the shower valve boxes & associated pipework into both the wetrooms. In addition to that the water pipes & basin drains have also been installed to match roughly where the bathroom furniture will go.
The wetroom shower trays had a further skim of concrete onto them, which has removed the dogs paw prints !
Plaster board has continued to be installed - this time in the outer workroom - looks like another bit of the house now ! In addition the fire proof board has been completed & most of the roof sections are now done.
The lads have also been out with the cement & brinks & begun patching up the workshop wall & join to the main house. In addition the path at the rear of the house has been repaired (where it was dug up for the drains).
The stairs were measured up today as well, and Doug brought round some sample spindles. Think we'll go for the simple oak design, which will be nicely understated. Not sure how long this will take to make, but it can't go in until the plaster board is finished off.
0 comments:
Post a Comment