Sunday, 29 August 2010
Days 80 & 81 - Ames taping begins
As the title says, the tapers were here both Saturday (all day) and Sunday morning. They've made really good progress & the house has been transformed ! Still a way to go, and the plaster/filler needs time to dry out, but looking good !
The joiners were also here on Saturday morning & continued with the window sills upstairs.
In between the rain (which was going on all weekend !) I managed to get the remaining sections of the existing roof cleaned up & the moss removed. When we get a dryer spell I can apply the moss killer & preventer stuff.
Work this coming week is to start in the dining room, so we've been busy clearing that out ready, along with the cupboard in the hall & the laundry area. Not sure how long it's going to take at this end, and it's going to be a bit disruptive...
0 comments:
Post a Comment