Day 78 - First windowsill goes in

The lads have started on the window sills upstairs - they're MDF type material with a wood veneer which can be stained. Look fine so far, and seem to be glued in place rather than nailed (so quite neat). Also a lot of work done out at the workshop - the partition is in place, insulation in & most of the plaster board in place. Wood strapping has been put on the outside wall near the heating pipes too & the sink drain hole bored through the wall.
Plumber has been carrying on with the bathroom pipework. Looks like all the water feed pipes are now in - shame that the plasterboard has had to go up & down a few times to achieve this....
Clean up planned for tomorrow, and apparently we'll see the first of the tapers on Saturday.