Just as we hoped, the lads managed to lay the remaining heating pipes & fix in place (on top of the insulation). Looking really good, and is now ready for further concrete pour on top. Weather has been good today, so if things hold out like this we should see the floor completed this week, as planned.
Although the heating was the main feature today, further rendering was completed with most of the lower walls having their top layer applied & smoothed off. Intend to have a final top coat with a colour pigment to match the existing house block work in due course.