Day 110 - Ground grading at the front

Doug was back with the digger this morning & graded the driveway towards the new rear entrance - this is to satisfy Planning Regs for wheelchair access, and is a real pain. We're still not convinced that this is going to look ok, so Andrew the architect is coming by on Tuesday so we can run through things.
Doug also cleared up a lot of the gear that's been lying around the drive for the past few weeks, so things looking a bit neater now.
One of the joiners was in this morning, and has completed the skirting in both Jenny's & the guest bedrooms.
The plumber also came by & finished the 1st floor radiators (all 3 working now) and installed the 2 toilet vents through the roof. His sparky will be here on Monday to get after the electric work required for the underfloor heating & the hot water loop pump.
Also today we got the WC cabinet worktop from Atlantis (the one we were missing) and await the replacement vanity unit worktop & a replacement mirror cupboard for the ensuite. Should get all that within the next 14 days, but it's not holding anything up.
I also completed all but 2 of the media points in the rooms (Jenny's, family room & hall cupboard), so only a couple more to do - just need to get the necessary faceplates, as the sparkies put the wrong ones in for some reason.