Tuesday, 12 October 2010

Day 117 - Bannisters & spindles on first floor

The joiners made some great progress with the stairs today and have installed the spindles & bannisters up the staircase & on the first floor. Still some finishing work to do, but we're almost there with them.
Other joinery saw the airing cupboard door facings installed inside, and the loft hatch installed in the new garage hallway.
The lads also lifted the vinyl tiles in the laundry & prepped some hardboard ready for the tiling to be done in there shortly (heard that the tiles should be in by next Wednesday).
The underlay for the oak flooring is due to arrive tomorrow, so we should see a start being made to that, and I estimated that will be finished by the weekend ready for the painting & plastering squad arriving.

0 comments:

Post a Comment