Monday, 25 October 2010

Day 127 - Ensuite cabinet in

The replacement ensuite cupboard was installed today, although the doors have yet to be fitted. Some more of the skirting boards were also put up, so not much left there to do. Apart from that there's not much sign of other work that was completed by the joiners today (although I'm sure there must be more). Still no sign of the replacement front vestibule windows, but hoping they'll arrive soon so that we can get that area finished off.
The painter also carried on, and has varnished some more of the window frames & sills. Unfortunately the ones that were to be reworked in the upstairs lounge don't look to be any better, but have been varnished anyway. Will need to find out more on this. Still no staining done in the main wet room and the study (though the study has a fair bit of oak boards in it yet).