Day 130 & 131 - Power in the garage and a workshop

There have been loads of folk working here over the last couple of days, as we move towards completion by the end of next week.
The sparky was here on Thursday and prepped up the two wetrooms for the shaver & light fittings. Still to complete though, and the extractor has yet to go in. The garage electrics were mostly completed too though, including the new workshop, so that has made a real difference. Sparky expected back early next week to complete things.
The joiners completed the garage workshop, which is looking really smart. The skirting & door is on (with a lock) and they've fitted a neat window to keep some light in the garage. The joiners have also been working up in the attic and have layed some more insulation - a good thing as the temperature has been dropping a bit of late.
The painter has mostly finished upstairs, though I'm still not impressed by a couple of the windows that were stained incorrectly previously. Looking like we'll need to sort this ourselves to get it right. Still more staining & varnishing to do downstairs, but upstairs should be ready for the emulsion coats early next week.
Unfortunately we're still waiting on the 2 final windows to arrive to finish the front entrance. They were meant to come on Monday - but which Monday !!