Wednesday 22 September 2010

Day 103 - Wetroom units going in

Joiners & the plumber set about the main wet room today & have started installing the units & brasswear. The shower is in & working, the wall hung vanity unit is also in place, along with the toilet unit. Sink & pan are in place, but wastes need to be connected up yet. Plumber seems to be having a bit of hassle with the waste off the sink, but should hopefully get it sorted out tomorrow. Tap looks really good, and has a nice solid feel to it.
Tomorrow the lads will carry on & we should hopefully see it complete. Still got a mirror cupboard to install, a smaller wall unit, electrics and bits such as the towel rail etc.
Sparks were also here & fitted all the outside soffit lighting. Also did a bit more work inside sorting out switches & sockets. The new BT phone point is also in place in the new hall. They're back again tomorrow too.
Joiners were again carrying on with the larch, but fitted another new door to the new hall cupboard. Still a few doors to do yet..
As well as this activity, the laminate for the work room arrived (the stuff that cost almost as much as the delivery charge !). Also ordered another WC unit counter top from Atlantis, as the original order had missed one out (for the ensuite). Cat6a wall sockets also arrived, so will be able to get after some of them in the coming days - though still waiting for some F-Module satellite connections.

0 comments: