Day 106 - Garage harled

The rest of the squad were back at work today following the long weekend. The slaters were also here, which was a boost. They harled the garage & completed the details around the garage windows & boiler exhaust. Looks really good. They also put up the bulk of the gutter downpipes, though one at the back of the house is blocking the outside socket, so something will need to give !
The joiners continued with the cladding, and the area around the new rear door is completed, including the detail work up by the soffits & under the eaves. They also carried on inside & made a start to the ensuite units - though there's been an error in the worktop, so we'll need to replace that unfortunately.
The tiler was also here for a while & completed the grouting in the ensuite, so that should be him I think (though there's some grout to go in at the wall in the shower area).
Tomorrow the plumber is back, so we should see the main wet room completed & a start made on the ensuite brass wear. Still no idea when the plumber's sparky is coming - we need him to get the underfloor heating sorted out.....

0 comments:

Post a Comment