Thursday 23 September 2010

Day 104 - More outside lights !

Sparkies were back again today and did a fair bit. They installed all 3 of the outside door lights (the stainless up & down type), and they look really good. These are the IP44 type ones, which is just as well as all of them have been soaked with the heavy rain today. They also got the BT socket moved from the diningroom to the front hall, so finally the lump of wires across the door has been moved. Finally they sorted out the lights in the kitchen & diningroom - got rid of the hideous down lighters & installed ceiling pendants. We'll change these later for different units, but fine for now.
Joiners sorted a few more doors out - the door from the dining room to the front vestibule is in, and the original front hall cupboard door has been modified & put back in. The vanity unit in the main wetroom has also been completed with the door & drawer now fitted.
Plumber was also here and has (mostly) plumbed in the WC. Still needs bolted to the floor & the vacuum flusher needs fitted yet (was some confusion over that one today apparently). The sink is also plumbed in, but the waste isn't what I expected. The sprung plug is different & the bottle trap hasn't been used. Will need to find out what's happened there.
The lads are now off for the bank holiday weekend (yes, another one !), so won't be back until next Tuesday. Guess that gives us some time to catch up on other things....

0 comments:

Post a Comment